AFAC

AFFARS

EXPLANATION OF CHANGE

5301

5301.601-Eliminates the separation of general contracting authority from Head of Contracting Activity (HCA) authority. 5301.603-1-Eliminates the reference to general contracting authority. 5301.603-2-90-Relocates warranting information from 5318 and editorial changes. 5301.101, 5301.170, 5301.170-4, 5301.201-1, 5301.304, 5301.402, 5301.403, (S-90), 5301.404, (S-90), 5301.601-91, 5301.602-3, 5301.9001, 5301.9102-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. 5301.601-91-Changes Contracting Self-Assessment Program to Self Inspection Program. 5301.602-2(c)(i)(B)-Changes Legal Review threshold. 5301.9001(f)(1)(i), (2),(3)(5)-Editorial changes. 5301.9000(a)(7),(b)(2),(e)(1)-Revised for clarity.

5302

5302.101-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC-“AFICA”, “AFICA/K_”, “Chief of the Contracting Office”, “Senior Contracting Official”, “Senior Center Contracting Official”. “DAS(C)”-Editorial change.

5303

5303.104-5, 5303.104-7, 5303.104-9, 5303.602, 5303.705, 5303.1003, 5303.1104-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. 5303.104-4(a)-Editorial change.

5304

5304.803-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. 5304.402(a)-Updates AFI reference. 5304.7003-90-Reworded for clarity.

5305

5305.202, 5305.303(a)(ii)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5306

5306.302-2(c)(1), 5306.304(a), 5306.501-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5307

5307.104-92-Reworded for clarity, 5307.104-92(b), 5307.104-93, 5307.170-3(a)(3)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. 5307.170-3(a)(3)-Editorial changes.

5308

NO CHANGES

5309

5309.405(a), 5309.406-3(a)(i), 5309.503, 5309.504(c)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5310

NO CHANGES

5311

5311.273-3(3)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. 5311.603-Updates AFI reference.

5312

NO CHANGES

5313

NO CHANGES

5314

NO CHANGES

5315

5315.403-1(c), 5315.403-4(a)(2), 5315.406-1(b)(ii)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5316

5316.206-3(d), 5316.405-2(1), 5316.504(c)(1)(ii)(D)(1)(i), 5316.601(d)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. 5316.504(a)(2)-Editorial changes. 5316.102 language moved to 5316.401(d) for proper alignment with FAR/DFARS.

5317

5317.170-Numbering changes to align with DFARS. 5317.500-Updates AFI and MP references. 5317.7404-3-Editorial changes. 5317.7802-moved to 5317.770 to conform to DFARS. 5317.170, 5317.171, 5317.172, 5317.174, 5317.204, 5317.7402, 5317.7404-3, 5317.404-5, 5317.7405-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC

5318

5318.201-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC, makes editorial changes, and moves language regarding contingency contracting warrants to 5301.603-2-90.

5319

5319.201(d)(10)(B), 5319.505(d), 5319.810-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5320

RESERVED

5321

RESERVED

5322

NO CHANGES

5323

NO CHANGES

5324

RESERVED

5325

5325.1001(a)(2)(iii), 5325.7002-2(b)(1)(iv), 5325.7003-3-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5326

RESERVED

5327

NO CHANGES

5328

5328.305(d)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. 5328.370(b)(1)-Added cross reference to MP5301.601(a)(1).

5329

RESERVED

5330

5330.201-5-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5331

NO CHANGES

5332

5332.703-2(a)-Deletes obsolete reference. 5332.104, 5332.202-1(b)(8), 5332.402(e)(2), 5332.501-2(a)(3), 5332.501-3(a), 5332.607(a)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5333

5333.103(d)(4), 5333.104, 5333.105, 5333.170, 5333.290(b)-(c), 5333.291(b), 5333.292(b)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5334

RESERVED

5335

NO CHANGES

5336

NO CHANGES

5337

5337.106-Deletes obsolete reference. 5337.204-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5338

RESERVED

5339

NO CHANGES

5340

RESERVED

5341

NO CHANGES

5342

42.1503(a)(1), (h)(3)-Editorial changes.

5343

5343.204-70-1(b), 5343.204-70-7-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5344

RESERVED

5345

5345.102(e)(4)(ii)(C)(1)(i)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5346

NO CHANGES

5347

RESERVED

5348

NO CHANGES

5349

5349.101(b), 5349.402-6(c), 5349.501-70, 5349.7001, 5349.7003(b)(2)(i) -Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5350

5350.103-5(a), 5350.104-3(b)(1)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5351

RESERVED

5352

5352.201-9101(c)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. 5352.237-9001-Deletes “RESERVEDplaceholder.

5353

RESERVED

MP5301.170(a)

3.-Editorial change. 4.-Added to provide coordination instructions for post-award peer reviews of Service Contracts.

MP5301.4

NO CHANGES

MP5301.601(a)(i)

Note 1-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. Items #2 and #3 and Note 3-Adds HCA delegations regarding grants and other transactions, and the authority to enter into contracts. #98 to #73-moved to align with DFARS 228. Adds Item #88-add approval of determination to allow more than five offerors to submit phase two design-build proposals for acquisitions >$4M.

MP5301.601-91

Global changes of the program name from “Self-Assessment” to “Self Inspection”. 2., 3.-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. 3.-Editorial change.

MP5301.602-2(d)

5.1-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. Opening Para. 1.4.1(b), 1.4.5, 1.4.8(n)-(o)-(p), 1.4.9, 1.12, 1.13., 5.3, 5.3.1(b), 5.3.2(b)-Editorial changes.

MP5301.602-3

5.-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

MP5301.603

2.2., 2.2.1., 4.1.1.-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. 1.1., 2.2., 2.2.1., 2.4., 2.6.2., 2.7., 2.9., 2.10.1., 3.2., 3.3., 3.3.1., 3.3.3., 3.3.5., 3.3.6., 3.3.7., 3.3.8., 3.3.9., 3.3.10., 3.4., 3.5.4., 3.5.6., 3.5.7., 4.1., 6.—Editorial changes.

MP5301.9001(b)

3.1.-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

MP5301.9001(f)

1.a., 2.-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. 1.c.-Editorial changes.

MP5303

MP5303.104-5(b), MP5303.602-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

MP5305.303

NO CHANGES

MP5306.502

1., 1.3., 2.2, 2.5., 2.6., 2.7., 2.12., 2.13., 3.1., 3.1.1., 3.1.2., 3.2.1., 3.2.2., 3.2.3., 4.1. 4.1.1.-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

MP5315.3

1.3., 1.4.1.1.(Note 5.), 6.2-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. 4.9-Template list updated.

MP5315.4

3.d.-Adds reference and hyperlink to a recommended elevation process contained in the Air Force Streamlining Guide.

MP5315.407-90

3.-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

MP5315.407-91

NO CHANGES

MP5315.606-90

(a), (b)(2)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

MP5316.504

NO CHANGES

MP5317.5

MP5317.502-2(b)-Updates AFFARS reference.

MP5317.74

2.c.-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

MP5317.770

Previously MP5317.78. Renumbered to align with DFARS.

MP5319

NO CHANGES

MP5325

NO CHANGES

MP5325.7002-2

2.-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

MP5325.7003-3

2., 3.-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

MP5332.470

(1)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

MP5332.7

(c)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

MP5333.104

(a)(4), (a)(5), (f)(1)(ii)(A), (g)(4)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

MP5342.902

NO CHANGES

MP5346.103

Introduction-Revised for clarity.

MP5349

NO CHANGES

MP5350.103-5

NO CHANGES

IG5315.404-3

NO CHANGES

IG5317.74

NO CHANGES

IG5317.9000

NO CHANGES

5301

5301.601-Eliminates the separation of general contracting authority from Head of Contracting Activity (HCA) authority. 5301.603-1-Eliminates the reference to general contracting authority. 5301.603-2-90-Relocates warranting information from 5318 and editorial changes. 5301.101, 5301.170, 5301.170-4, 5301.201-1, 5301.304, 5301.402, 5301.403, (S-90), 5301.404, (S-90), 5301.601-91, 5301.602-3, 5301.9001, 5301.9102-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. 5301.601-91-Changes Contracting Self-Assessment Program to Self Inspection Program. 5301.602-2(c)(i)(B)-Changes Legal Review threshold. 5301.9001(f)(1)(i), (2),(3)(5)-Editorial changes. 5301.9000(a)(7),(b)(2),(e)(1)-Revised for clarity.

5302

5302.101-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC-“AFICA”, “AFICA/K_”, “Chief of the Contracting Office”, “Senior Contracting Official”, “Senior Center Contracting Official”. “DAS(C)”-Editorial change.

5303

5303.104-5, 5303.104-7, 5303.104-9, 5303.602, 5303.705, 5303.1003, 5303.1104-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. 5303.104-4(a)-Editorial change.

5304

5304.803-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. 5304.402(a)-Updates AFI reference. 5304.7003-90-Reworded for clarity.

5305

5305.202, 5305.303(a)(ii)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5306

5306.302-2(c)(1), 5306.304(a), 5306.501-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

Justification Value

Approval Authority

Delegability

< $700K

Chief of the Contracting Office

Delegable to Contracting Officer, consistent with warrant level

> $700K < $13.5M

Procuring Activity
Competition Advocate

Not further delegable

> $13.5M < $93M

PEO / Head of Procuring Activity / Designated Alternate if they meet the criteria in FAR 6.304(a)(3). If they do not meet the criteria in FAR 6.304(a)(3) = Senior Procurement Executive

Delegable to Flag / General Officer or civilian SES

> $93M*

Senior Procurement Executive

Not further delegable

5307

5307.104-92-Reworded for clarity, 5307.104-92(b), 5307.104-93, 5307.170-3(a)(3)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. 5307.170-3(a)(3)-Editorial changes.

Acquisition Strategy Panels

Acquisition Type

ASP Chairperson

ACAT or Special Designated Programs

See AFI 63-101

PEO - Services

See AFI 63-138

Other Contracting - Supplies

MAJCOM/DRU/AFRCO SCO (or for AFLCMC and SMC, the SCCO) or designee

Other Contracting - Services

Services Designated Official (SDO) or designee; when no SDO, the MAJCOM/DRU/AFRCO SCO (or for AFLCMC and SMC, the SCCO) or designee

AP Approval

Acquisition Type

Document

AP Approval Authority

PEO – Supplies

Acquisition Plan

See AFI 63-101

Other Contracting –
Supplies > $10M

Acquisition Plan

MAJCOM/DRU/AFRCO SCO (or for AFLCMC and SMC, the SCCO) or designee

Other Contracting –
Services > $10M

Acquisition Plan

SDO or designee; when no SDO, the MAJCOM/DRU/AFRCO SCO (or for AFLCMC and SMC, the SCCO) or designee

PEO – Services > $10M

Acquisition Plan

See AFI 63-138

> SAT < $10M

Streamlined Acquisition Strategy Summary (SASS) *

1 level above CO

    * AP may be prepared at the discretion of the CO or the approval authority for those actions where an AP would be more appropriate.

5309

5309.405(a), 5309.406-3(a)(i), 5309.503, 5309.504(c)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5311

5311.273-3(3)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. 5311.603-Updates AFI reference.

5315

 

5315.403-1(c), 5315.403-4(a)(2), 5315.406-1(b)(ii)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5316

5316.206-3(d), 5316.405-2(1), 5316.504(c)(1)(ii)(D)(1)(i), 5316.601(d)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. 5316.504(a)(2)-Editorial changes. 5316.102 language moved to 5316.401(d) for proper alignment with FAR/DFARS.

5317

5317.170-Numbering changes to align with DFARS. 5317.500-Updates AFI and MP references. 5317.7404-3-Editorial changes. 5317.7802-moved to 5317.770 to conform to DFARS. 5317.170, 5317.171, 5317.172, 5317.174, 5317.204, 5317.7402, 5317.7404-3, 5317.404-5, 5317.7405-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC

5318

5318.201-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC, makes editorial changes, and moves language regarding contingency contracting warrants to 5301.603-2-90.

5319

5319.201(d)(10)(B), 5319.505(d), 5319.810-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5325

5325.1001(a)(2)(iii), 5325.7002-2(b)(1)(iv), 5325.7003-3-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5328

5328.305(d)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. 5328.370(b)(1)-Added cross reference to MP5301.601(a)(1).

5330

5330.201-5-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5332

5332.703-2(a)-Deletes obsolete reference. 5332.104, 5332.202-1(b)(8), 5332.402(e)(2), 5332.501-2(a)(3), 5332.501-3(a), 5332.607(a)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5333

5333.103(d)(4), 5333.104, 5333.105, 5333.170, 5333.290(b)-(c), 5333.291(b), 5333.292(b)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5337

5337.106-Deletes obsolete reference. 5337.204-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5342

42.1503(a)(1), (h)(3)-Editorial changes.

5343

5343.204-70-1(b), 5343.204-70-7-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5345

5345.102(e)(4)(ii)(C)(1)(i)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5349

5349.101(b), 5349.402-6(c), 5349.501-70, 5349.7001, 5349.7003(b)(2)(i) -Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5350

5350.103-5(a), 5350.104-3(b)(1)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

5352

5352.201-9101(c)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. 5352.237-9001-Deletes “RESERVEDplaceholder.

MP5301.170(a)

3.-Editorial change. 4.-Added to provide coordination instructions for post-award peer reviews of Service Contracts.

MP5301.601(a)(i)

Note 1-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. Items #2 and #3 and Note 3-Adds HCA delegations regarding grants and other transactions, and the authority to enter into contracts. #98 to #73-moved to align with DFARS 228. Adds Item #88-add approval of determination to allow more than five offerors to submit phase two design-build proposals for acquisitions >$4M.

MP5301.601-91

Global changes of the program name from “Self Assessment” to “Self Inspection”. 2., 3.-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. 3.-Editorial change.

MP5301.602-2(d)

5.1-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. Opening Para., 1.4.1.(b), 1.4.5, 1.4.8(n)-(o)-(p), 1.4.9, 1.12, 1.13., 5.3, 5.3.1(b), 5.3.2(b)-Editorial changes.

MP5301.602-3

5.-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

MP5301.603

2.2., 2.2.1., 4.1.1.-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. 1.1., 2.2., 2.2.1., 2.4., 2.6.2., 2.7., 2.9., 2.10.1., 3.2., 3.3., 3.3.1., 3.3.3., 3.3.5., 3.3.6., 3.3.7., 3.3.8., 3.3.9., 3.3.10., 3.4., 3.5.4., 3.5.6., 3.5.7., 4.1., 6.—Editorial changes.

MP5301.9001(b)

3.1.-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

MP5301.9001(f)

1.a., 2.-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. 1.c.-Editorial changes.

MP5303

MP5303.104-5(b), MP5303.602-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

MP5306.502

1., 1.3., 2.2, 2.5., 2.6., 2.7., 2.12., 2.13., 3.1., 3.1.1., 3.1.2., 3.2.1., 3.2.2., 3.2.3., 4.1. 4.1.1.-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

MP5315.3

1.3., 1.4.1.1.(Note 5.), 6.2-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC. 4.9-Template list updated.

MP5315.4

3.d.-Adds reference and hyperlink to a recommended elevation process contained in the Air Force Streamlining Guide.

MP5315.407-90

3.-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

MP5315.606-90

(a), (b)(2)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

MP5317.5

MP5317.502-2(b)-Updates AFFARS reference.

MP5317.74

2.c.-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

MP5317.770

Previously MP5317.78. Renumbered to align with DFARS.

MP5325.7002-2

2.-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

MP5325.7003-3

2., 3.-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

MP5332.470

(1)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

MP5332.7

(c)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

MP5333.104

(a)(4), (a)(5), (f)(1)(ii)(A), (g)(4)-Incorporates Policy Memo 15-C-02, Changes to Contracting Authority to Support the Inclusion of AFICA Into AFIMSC.

MP5346.103

Introduction - Revised for clarity.

Item

Reference

HCA Responsibilities / Designee

Retained by HCA
(SAF/AQC)

Delegated to SCOs, SCCOs, or Delegable to SCCOs
(Notes 1 & 2)

Delegable below SCO or
SCCOs
(Notes 1 & 2)

1

    FAR 1.602-3(b)(2) and (3)
    AFFARS 5301.602-3(b)(2)

Ratification of unauthorized commitments, subject to the limitations in FAR 1.602-3(c) -- Delegated in AFFARS

No

Yes, for actions of $30K and above

Delegated to the COCO for actions less than $30K (not redelegable)

2

AFFARS 5301.601(a)(i)(A)

Authority to enter into, approve, or terminate Grants, Cooperative Agreements, and Other Transactions—including the issuance of a warrant for such purposes.

See Note 3

See Note 3

Yes,
See Note 3

3

AFFARS 5301.601(a)(i)(A)
AFFARS 5301.603-1

Authority to enter into, approve, modify, and terminate contracts—including the issuance of a Contracting Officer warrant for such purposes.

No

Yes,
See Notes 1 and 2

Yes,
See 5301.603-1

4

FAR 3.104-5(c)(2)
AFFARS 5303.104-3(c)(1)(ii)

Authorizes the disqualified official to resume participation in the procurement or determine that an additional disqualification period is necessary.

No

Yes

No

5

FAR 3.104-7
AFFARS 5303.104-7(f)

Reviews and takes appropriate action on information that a reported violation or possible violation of a present or former government official or someone advising that official knowingly disclosed contractor bid or proposal information or source selection information before award.

Yes

No

No

6

FAR 3.602
AFFARS 5303.602

Authorizes contract award to a Government employee or to a business concern owned or controlled by a Government employee and only if there is a most compelling reason to do so per FAR 3.602.

Yes

No

No

7

FAR 3.704(c)
AFFARS 5303.704(c)

Considers, in addition to any penalty prescribed by law or regulation--suspension or debarment proceedings, voiding and rescinding contracts for a contractor convicted of any offense relating to contracts with the agency.

No

Yes

No

8

FAR 3.1104(b)
AFFARS 5303.1104(b)
FAR 9.504(c)
AFFARS 5309.504(c)

Determines in writing that such action in FAR 3.1104(a) is in the best interest of the Government (HCA may impose conditions that provide mitigation of a personal conflict of interest or grant a waiver)

Yes

No

No

9

DFARS 205.502(a)
AFFARS 5305.502(a)

Approves the publication of paid advertisements in newspapers. -- Delegated in AFFARS

No

Yes

Yes, one level above CO

10

DFARS 206.302-1(a)(2)(i)(1)
AFFARS 5306.302-1(a)(2)(i)(1)

Determines if agency can enter into contracts for studies, analyses, or consulting services on the basis of an unsolicited proposal without providing for full and open competition.

No

Yes

Yes, but no lower than the COCO

11

FAR 6.302-1(d)
DFARS 206.302-1(d)
DFARS PGI 206.302-1(d)
AFFARS 5306.302-1(d)

Approves waiver to post request for information or sources sought notices when using J&A authority FAR 6.302-1.

No

Yes, only if SCO/SCCO is GO or SES

No

12

DFARS 206.302-4(c)
AFFARS 5306.302-4(c)

Approves a document (AFFARS prescribes use of International Agreement Competitive Restrictions (IACR)) that describes the terms of an agreement or treaty or written directions, such as a Letter of Offer and Acceptance, which have the effect of requiring the use of other than competitive procedures. J&A is not required. -- Delegated in AFFARS

No

Yes

Yes, CO

13

DFARS 207.470(b)
AFFARS 5307.470(b)

Approves acquisition for vessel/aircraft/vehicle through a lease/charter/similar agreement for 18 months or more.

No

Yes

No

14

FAR 8.404(h)(3)(ii)(C)
AFFARS 5308.404(h)(3)(ii)(C)

Approves D&F when the total performance period, including options, of a T&M/LH order is more than three years.

No

Yes

No

15

FAR 9.202(a)
DFARS PGI 209.202(a)(1)
AFFARS 5309.202(a)(1)

Is the designee referenced in FAR 9.202(a) (inclusion of other qualification requirements).

No

Yes

Yes, but no lower than COCO

16

FAR 9.206-1(b)
AFFARS 5309.206-1(b)

Is the designee referenced in FAR 9.206-1(b) (enforcing qualification requirements).

No

Yes

Yes, but no lower than COCO

17

DFARS 209.270-3(a)
AFFARS 5309.270-3(a)

Approves a contract for procurement, modification, repair, or overhaul of an aviation critical safety item with a source approved by the head of the design control activity.

No

Yes

Yes, but no lower than COCO

18

FAR 9.503 / 9.506(d)(3)
AFFARS 5309.503

Waives FAR 9.5 requirements -- Organizational and Consultant Conflicts of Interest (OCI).

Yes

No

No

19

DFARS 209.571-7(b)(2)(c)(1)
AFFARS 5309.571-7(c)(1)

Determines an exception to Limitation on Future Contracting in systems engineering and technical assistance contracts is necessary.

Yes

No

No

20

DFARS PGI 211.273-3
AFFARS 5311.273-3(3)

Determines prior to contract award, that a Single Process Initiative (SPI) process for use in lieu of military or Federal specifications and standards is not acceptable for a specific procurement.

Yes

No

No

21

DFARS 211.274-2(b)(2)(i)((B)
AFFARS 5311.274-2(b)(2)(i)(B)

Determines it is more cost effective for the Government requiring activity to assign, mark, and register unique item identification after delivery of an item acquired from a small business concern or a commercial item acquired under FAR Part 12 or Part 8 for an acquisition other than ACAT I program.

No

Yes

No

22

DFARS 212.302(c)
AFFARS 5312.302(c)

Waiver authority for tailoring provisions and clauses for acquisition of commercial items under FAR 12.302(c).

No

Yes

No

23

FAR 14.201-7(b)(2) and (c)(2)
AFFARS 5314.201-7(b)(2) and (c)(2)

Waives the requirement for inclusion of FAR clauses 52.214-27 and 52.214-28 in a contract with a foreign government or agency of that government.

No

Yes

No

24

DFARS 215.371-5
AFFARS 5315.371-5

Waives the requirement at DFARS 215.371-2 to resolicit for an additional period of at least 30 days when only one offer is received as a result of a competitive solicitation allowing fewer than 30 days for receipt of proposals.

No

Yes

Yes, but no lower than the COCO

25

FAR 15.403-1(c)(4)
DFARS 215.403-1(c)(4)(A)
AFFARS 5315.403-1(c)(4)(A)

Waives requirement for submission of certified cost or pricing data in exceptional cases.

Yes

No

No

26

FAR 15.403-3(a)(4)
AFFARS 5315.403-3(a)(4)

Approves determination to make award without offeror submission of data other than certified cost or pricing data.

No

Yes

No

27

FAR 15.403-4(a)(2)
AFFARS 5315.403-4(a)(2)

Authorizes CO to obtain certified cost or pricing data for actions below the threshold in FAR15.403-4(a)(1), provided the action exceeds the SAT.

Yes

No

No

28

DFARS 215.404-4(c)(2)(C)(2)
AFFARS 5315.404-4(c)(2)(C)(2)(90)

Approves the use of the alternate structured approach for Profit (see DFARS 215.404-73). -- Delegated in AFFARS

No

Yes

Yes, but no lower than COCO

29

DFARS 215.407-3(b)(i)
AFFARS 5315.407-3(b)(i)

Waives on a case-by-case basis, the use of forward pricing rate agreement (FPRA) rates when such rates are available.

No

Yes

No

30

DFARS PGI 215.407-4(c)(2)(B)
AFFARS 5315.407-4(c)(2)(B)

Requests an overhead should-cost review for a contractor business unit that does not meet the criteria found in DFARS PGI 215.407-4(c)(2)(A).

No

Yes

No

31

DFARS 215.408(3)(i)(A)(2)
AFFARS 5315.408(3)(i)(A)(2)

Approve determination (when contracting with the Canadian Commercial Corporation) that data other than certified cost or pricing data are needed in order to determine that the price is fair and reasonable. Delegated in AFFARS.

No

Yes

Yes, two levels above the Contracting Officer

32

DFARS 215.408(3)(ii)(A)(2)
AFFARS 5315.408(3)(ii)(A)(2)

Approve determination (when contracting with the Canadian Commercial Corporation) that it is reasonably certain that data other than certified cost or pricing data will be needed in order to determine that the price of modifications is fair and reasonable. Delegated in AFFARS.

No

Yes

Yes, two levels above the Contracting Officer

33

FAR 16.206-3(d)
AFFARS 5316.206-3(d)

Approves the use of a fixed-ceiling-price contract with retroactive price redetermination.

Yes

No

No

34

FAR 16.401(d)
DFARS PGI 216.401(e)
AFFARS 5316.401(d)

Approves D&F to justify that the use of an incentive or award-fee contract is in the best interest of the government.

Yes, if award fee is for (a) all ACAT I or II programs and (b) non-ACAT I or II contracts with estimated value of $50M or more.
No, for all others.

Yes

No

35

AFFARS 5316.401(e)(3)(i)

For Other Contracting, the HCA will designate the Fee Determining Official. The PEO is the Fee Determining Official for the PEO’s assigned programs. The PEO or HCA for Other Contracting may designate this responsibility on an individual contract or class basis. This designation may be made by name, position, or function, without limitation.

No

Yes, for Other Contracting

Yes, for Other Contracting

36

DFARS 216.405-2(1)
AFFARS 5316.405-2(1)

Approves setting the percentage of award fee available for the final evaluation below 40 percent if the contracting officer determines that a lower percentage is appropriate.

Yes

No

No

37

FAR 16.601(d)
DFARS 216.601(d)
AFFARS 5316.601(d)(1)(A)(2)
Class Deviation 2012-O0016

Approves the D&F for a T&M/LH contract or order if the base period plus any option period exceeds three years.

Yes

No

No

38

FAR 16.603-2(c)(3)
AFFARS 5316.603-2(c)(3)

Gives CO approval to determine a reasonable price or fee if the CO & contractor fail to reach agreement.

No

Yes

No

39

FAR 16.603-3
AFFARS 5316.603-3

Determines a letter contract may be used if no other contract type is suitable.

No

Yes

AFMC and SMC SCCOs, and the AFRCO SCO only may delegate below $50M to no lower than COCO

40

FAR 17.106-3(f)
AFFARS 5317.106-3(f)

Authorizes the use of a solicitation requesting only multi-year prices, provided that dual proposals are not necessary to meet the objectives in FAR 17.105-2.

No

Yes

No

41

FAR 17.106-3(g)
AFFARS 5317.106-3(g)

Approves the use of variable unit prices on multi-year contracts provided that, for competitive proposals, there is a valid method of evaluation.

No

Yes

No

42

DFARS 217.172(e)(2)
AFFARS 5317.172(e)(2)

Determines the conditions required by DFARS 217.172(g)(2)(i)-(vii) will be met by a multi-year contract.

Yes

No

No

43

DFARS 217.174(b)
AFFARS 5317.174(b)

Determines, on the basis of a business case analysis, that the proposed purchase of electricity from sources of renewable energy under such contract is cost effective; and it would not be possible to purchase electricity from the source in an economical manner without the use of a contract for a period in excess of five years.

Yes

No

No

44

DFARS 217.7404-1
AFFARS 5317.7404-1

Approves Undefinitized Contract Actions (UCA).

No

Yes

AFMC and SMC SCCOs, and the AFRCO SCO only may delegate below $50M to no lower than COCO

45

DFARS 252.217-7027(c)

Approves unilateral definitizations by Contracting Officer.

No

Yes

AFMC and SMC SCCOs, and the AFRCO SCO only may delegate below $50M to no lower than COCO

46

DFARS PGI 217.7504(4)(ii)
AFFARS 5317.7504(4)(ii)

Authorizes reverse engineering.

No

Yes

No

47

DFARS 217.7505(b)
AFFARS 5317.7505(b)

Approves Contracting Officer certification for a replenishment part price increase that increased by 25 percent or more over the most recent 12-month period.

No

Yes

No

48

FAR 18.125
AFFARS 5318.125

Determines that the contracting process may continue after GAO has received a protest (See FAR 33.104(b) and (c)).

Yes

No

No

49

FAR 18.2
DFARS 218.271
AFFARS 5318.201
FAR 13.500(e)
FAR 13.201(g)(1)
AFFARS 5313.201(g)(1)
FAR 12.102(f)
FAR 2.101, Micro-purchase threshold, paragraph (3)
FAR 2.101, Simplified acquisition threshold

Determines that micro-purchases and simplified acquisitions of supplies or services are to be used in support of a contingency operation or to facilitate defense against or recovery from nuclear, biological, chemical, or radiological attack.

No

Yes

Yes, but no lower than the COCO

50

FAR 19.201(c)
AFFARS 5319.201(c)

Implements small business programs within their activities, achieve program goals, and ensure contracting personnel maintain knowledge of program requirements.

No

Yes

No

51

DFARS 219.201(d)(8)
AFFARS 5319.201(d)(8)

Assigns small business technical advisors to perform this function in accordance with DFARS 219.201(10).

No

Yes

No

52

FAR 19.502-3(a)(5)
AFFARS 5319.502-3(a)(5)

Authorizes a partial set-aside be made if there is a reasonable expectation that only two concerns (one large and one small) with capability will respond with offers.

No

Yes

No

53

FAR 19.505(b), (c), and (d)
DFARS 219.505(b)
AFFARS 5319.505(b)

Renders a decision regarding the CO’s rejection of an SBA recommendation.

No

Yes

Yes, but no lower than COCO

54

FAR 19.1305(d)
AFFARS 5319.1305(d)

Determines not to suspend action on the acquisition because urgent and compelling circumstances exist. Replies to SBA if SBA files an appeal for not restricting acquisition to HUBZone.

No

Yes

No

55

FAR 19.1405(d)
AFFARS 5319.1405(d)

Determines not to suspend action. Replies to SBA after receipt of a formal appeal from SBA concerning rejection of a set-aside for Service-disabled Veteran-owned Small Business.

No

Yes

No

56

FAR 22.101-1(e)
AFFARS 5322.101-1(e)

Designates programs for contractors to notify Government of actual or potential labor disputes.

No

Yes

Yes, but no lower than COCO

57

DFARS 222.101-3-70
PGI 222.101-3-70(b)(ii)
AFFARS 5322.101-3-70(b)(ii)

Submits impact reports on labor disputes to agency head when sufficient urgency warrants the attention of the agency head or when specifically requested.

No

Yes

No

58

FAR 22.406-13
DFARS 22.406-13
AFFARS 5322.406-13

For construction contracts, submits Semiannual Enforcement Reports to the labor advisor.

No

Yes

No

59

FAR 22.805(a)(8)
AFFARS 5322.805(a)(8)

Approves an urgent or critical award, without pre-award clearance from the Office of Federal Contract Compliance Programs (OFCCP), if OFCCP cannot complete the evaluation by required date. Applies for contracts/subcontracts $10M or more excluding construction.

No

Yes

No

60

FAR 22.1802(d)
AFFARS 5322.1802(d)

Waives the E-Verify requirement for a contract or subcontract or a class of contracts or subcontracts, either temporarily or for the period of performance.

Yes

No

No

61

DFARS PGI 223.370-4
AFFARS 5323.370-4(1)(i)(A)(2)

Waives the mandatory requirements for safety precautions for ammunition and explosives.

No

Yes

No

62

FAR 25.103(b)(2)(i)
DFARS 225.103
AFFARS 5325.103(b)
AFFARS MP5325(a)

Approves determination that an article/material/supply is not mined, produced, or manufactured in the United States in sufficient quantities of satisfactory quality.

No

Yes

No

63

DFARS 225.103(a)(ii)(B)(2)
AFFARS 5325.103(b)

Approves determination for a public interest exception, valued between the simplified acquisition threshold and $1.5M, for end products that are substantially transformed in the United States.

No

Yes

No

64

DFARS 225.103(b)(ii)(C)
AFFARS 5325.103(b)

Approves determination for article/material/supply, for $1.5M or more, not domestically available and award is to be made on other than a qualifying country or eligible end product.

No

Yes

No

65

FAR 25.202(a)(2)
DFARS 225-202(a)(2)
AFFARS 5325.202(a)(2)

Approves non-availability determination for domestic construction material.

No

Yes

No

66

DFARS 225.403(c)(ii)(A)
AFFARS 5325.403(c)(ii)(A)

Approves a national interest waiver for a purchase by an overseas purchasing activity if the product is critical for the support of U.S. forces stationed abroad.

No

Yes

No

67

FAR 25.603(a)(1)(i)
AFFARS 5325.603(a)(1)(i)

Approves Non-availability Determination (American Recovery and Reinvestment Act – Buy American Act – Construction Materials).

No

Yes

No

68

DFARS 225.7008(a)(2)
AFFARS 5325.7008(a)(2)

Waives restrictions on certain foreign purchases under 10 U.S.C. 2534(a).

No

Yes

No

69

FAR 28.105
AFFARS 5328.105

Approves using other types of bonds when acquiring particular supplies or services.

No

Yes

No

70

FAR 28.106-2(a)
AFFARS 5328.106-2(a)

Approves the use of a new surety bond during the performance of the contract. -- Delegated in AFFARS

No

Yes

Yes, but no lower than COCO

71

DFARS 228.311-1
AFFARS 5328.311-1

Waives the requirement for use of FAR clause 52.228-7, Insurance -- Liability to Third Persons.

No

Yes

No

72

DFARS 228.370(a)(2)
AFFARS 5328.370(a)(2)

Disallows the contractor to buy insurance for war-hazard losses. If so, the CO shall insert the clause at DFARS 252.228-7000.

No

Yes

No

73

AFI 10-220 [Ground and Flight Risk Clause prescription at 228.370(b)(1)]

Approving authority for designating/appointing primary and alternate Government Flight Representatives (GFR)

No

Yes

No

74

Class Deviation
2011-O0006
AFFARS 5331

Waives the requirements of FAR 31.

No

Yes

No

75

Class Deviation
2011-O0006
AFFARS 5331

Determine that incurrence of the Contribution in Aid of Construction (CIAC) tax is necessary to achieve the most beneficial business case for the Government and allowing the CIAC tax will result in significant benefits to the Government that outweigh the cost of allowing the tax.

No

Yes

No

76

FAR 32.202-1(d)
FAR 32.501-2(a)(3)
AFFARS 5332.202-1(d)

Approves unusual contract financing.

No

Yes

No

77

DFARS 232.901
AFFARS 5332.901(1)(i)(c)(ii)

Determines that conditions exist that limit normal business operations.

No

Yes

No

78

FAR 33.102(b)(3)(ii)
AFFARS 5333.102(b)(3)(ii)

At the request of the contractor, reviews agency records associated with a request for reimbursement of protest costs by the Government.

No

Yes

Yes, but no lower than the COCO

79

FAR 33.104(b)(1) or (c)(2)
AFFARS 5333.104(b)(1) or (c)(2)

Authorizes contract award notwithstanding a GAO protest before award, or continued contract performance notwithstanding a GAO protest after award.

Yes

No

No

80

FAR 33.104(g)
AFFARS 5333.104(g)

Reports to the GAO why their recommendations have not been followed by the agency not later than 5 days after the expiration of the 60-day response period.

Yes

No

No

81

DFARS 233.215(3)
AFFARS 5333.215(3)

Determines that continued performance is necessary pending resolution of any claim that might arise under or be related to the contract.

No

Yes

Yes, at least one level above CO

82

DFARS 235.015-70(c) & (d)(3)(ii)
AFFARS 5335.015-70(c) & (d)(3)(ii)

Approves special use allowance for research facility acquired by educational institutions.

No

Yes

No

83

FAR 36.208
AFFARS 5336.208

Approves concurrent performance of firm-fixed-price and other types of construction contracts at the same work site.

No

Yes

No

84

FAR 36.213-2(a)
AFFARS 5336.213-2(a)

Waives the requirement for pre-solicitation notices for proposed construction contracts expected to exceed the SAT.

No

Yes

No

85

DFARS 236.272(b)(1)
AFFARS 5336.272(b)

Authorizes the use of pre-qualifications for urgent or complex construction projects.

No

Yes

Yes, but no lower than COCO

86

DFARS 236.272(b)(2)
AFFARS 5336.272(b)

Approves the prequalification procedures of construction sources.

No

Yes

Yes, but no lower than COCO

87

FAR 36.301(b)(3)(vi)
AFFARS 5336.301(b)(3)(vi)

Establishes other criteria for use of two-phase design-build selection procedures.

No

Yes

Yes, but no lower than COCO

88

FAR 36.303-1(a)(4)
*Effective 15 Jun 2016

Approves determination to allow more than five offerors to submit phase two design-build proposals for acquisitions >$4M.

No

Yes,
and to AFICA OL Directors of Contracting

No

89

DFARS 236.570(b)(2)
AFFARS 5336.570(b)(2)

Approves use of a separate bid item for mobilization and preparatory work.

No

Yes

Yes, but no lower than COCO

90

FAR 36.602-3
AFFARS 5336.602-3

Oversees evaluation board functions for A&E contracts.

No

Yes

Yes, but no lower than COCO

91

FAR 36.609-1(c)(1)
AFFARS 5336.609-1(c)(1)

Determines that, in fixed-price A&E contracts, cost limitations are secondary to performance considerations and additional project funding can be expected, if necessary.

No

Yes

No

92

DFARS 237.104(b)(iii)(A)(2)
AFFARS 5337.104(b)(iii)(A)(2)

Approves a proposed personal services contract for services to be provided by individuals outside the U.S. and directly supports defense intelligence components or special operations command. Services must be urgent, cannot be obtained by other means, and are supporting DoD activities or programs outside the U.S.

No

Yes

No

93

DFARS 237.7401(c)
AFFARS 5337.7401(c)

Determines the services being acquired under contract with the local government are in DoD’s best interest.

No

Yes

Yes, but no lower than COCO

94

FAR 41.202(c)(2)
AFFARS 5341.202(c)(2)

Approves determination to pay the non-negotiated utility rates due to contract impasse.

No

Yes

Yes, but no lower than COCO

95

FAR 41.204(c)(1)(ii)
AFFARS 5341.204(c)(1)(ii)

Determines use of the area-wide contract for utility services is not advantageous to the Government.

No

Yes

Yes, but no lower than COCO

96

FAR 42.202(c)(2)
AFFARS 5342.202(c)(2)

Approves the delegation of additional functions to the CAO.

No

Yes

Yes, but no lower than COCO

97

DFARS PGI 242.7100(4)
AFFARS 5342.7100(4)

Approves the solicitation of voluntary refunds from a contractor.

No

Yes

No

98

FAR 45.102(e)
AFFARS 5345.102(e)

Determines installation or construction of Government property on contractor-owned real property in such a fashion as to become non-severable is necessary and in the Government’s interest.

No

Yes

No

99

DFARS 245.102(4)(ii)(C)(1)(ii)
AFFARS 5345.102(4)(ii)(C)(1)(ii)

Approves a determination and findings concluding that it is more cost effective for the Government requiring activity to assign, mark, and register the unique item identification after delivery of an item acquired from a small business concern or a commercial item acquired under FAR part 12 or part 8. (CAE must approve the determination and findings for an ACAT I program.)

No

Yes, for other than ACAT I programs

No

100

FAR 45.301(f)
AFFARS 5345.301(f)

Approves use of Government property for commercial use expected to exceed 25 percent of the total use of Government and commercial work performed.

No

Yes

No

101

FAR 48.104-3(a)
AFFARS 5348.104-3(a)
FAR 48.202

Determines if the cost of calculating and tracking collateral savings will exceed the benefits to be derived.

No

Yes

Yes, but no lower than COCO

MAJCOM/DRU/SMC

Grant Authority

Cooperative Agreement Authority

Other Transactions Authority

HQ AFMC/PK

Yes

Yes

Yes

HQ AFRC/A7K

No

No

No

SMC/PK

Yes

Yes

Yes

HQ AFDW/PK

Yes

Yes

No

10 CONS/CL

Yes

Yes

No

AFOTEC/A7K

No

No

No