Air Force Materiel Command Acquisition Circular (AFMCAC)

2007-10

31 March 2010

Summary of Changes

AFMCFAR SUPPLEMENT (2007 Edition)

The following changes are a result of an Air Force Acquisition Circular (AFAC) 2009-1030 dated 30 October 2009 changes and HQ AFMC/PK Policy Memo 2009-PK-003, 27 April 2009, Subject: Integrated Product Team Pricing and Negotiation Process. These changes are effective immediately.

All references to IPT/One Pass Pricing Changes were deleted from:

5301.9001(f)

5301.9002(b) “Request for Business/Contract Clearance” document

IG5301.9001(f)

IG5301.9002(e) Clearance Briefing charts

IG5301.9003(5)(e)

Administrative changes:

Corrected 5315.403-1(c)(5) Reference and Link:

From: AFFARS MP5315.3, “Prohibition on Obtaining Cost or Pricing Data,” paragraph (c)(5)(A)

To: AFFARS MP5315.403-1 “Prohibition on Obtaining Cost or Pricing Data,” paragraph (c)(5)(A)

Corrected 5315.403-5(90) Submission of Cost or Pricing Data:

From: Submission of Cost or Pricing Data, substantially as written, in Section L, if adequate price competition is anticipated by may not be realized and cost or pricing data would otherwise be required.

To: Submission of Cost or Pricing Data, substantially as written, in Section L, if adequate price competition is anticipated but may not be realized and cost or pricing data would otherwise be required.

IG5301.9003 – Deleted IPT related terminology “if using traditional or commercial pricing”.

IG5301.9003 – Deleted all Preliminary Price Negotiation Memorandum (PPNM) and Final PNM terminology.

IG 5301.9003(c) – Corrected statement that Contract Clearance is required for all competitive acquisitions requesting approval to award without discussions or requesting Final Proposal Revisions (FPRS).

IG 5301.9003(d) – Corrected statement that Contract Clearance is required for all noncompetitive contract actions requesting approval to award.

IG5301.9003 – Corrected formatting.