[Federal Register Volume 78, Number 235 (Friday, December 6, 2013)]

[Rules and Regulations]

From the Federal Register Online via the Government Printing Office [www.gpo.gov]

[FR Doc No: 2013-29146]

-----------------------------------------------------------------------

DEPARTMENT OF DEFENSE

Defense Acquisition Regulations System

48 CFR Parts 201, 204, 212, 216, 225, 227, and 252

Defense Federal Acquisition Regulation Supplement; Technical Amendments

AGENCY: Defense Acquisition Regulations System, Department of Defense (DoD).

ACTION: Final rule.

-----------------------------------------------------------------------

SUMMARY: DoD is making technical amendments to the Defense Federal Acquisition Regulation Supplement (DFARS) to provide needed editorial changes.

DATES: Effective December 6, 2013.

FOR FURTHER INFORMATION CONTACT: Mr. Manuel Quinones, Defense Acquisition Regulations System, OUSD(AT&L)DPAP(DARS), Room 3B855, 3060 Defense Pentagon, Washington, DC 20301-3060. Telephone 571-372-6088; facsimile 571-372-6094.

SUPPLEMENTARY INFORMATION: This final rule amends the DFARS as follows:

1. Revises the section heading at 201.603 for consistency with the FAR.

2. Corrects 204.7207(a) to conform to the FAR by changing ``clause'' to ``provision.''

3. Corrects typographical error at 203.906(1).

4. Removes 212.301(f)(xlii) as a result of changes under DFARS final rule 2013-D037, published on November 18, 2013.

5. Corrects cross-reference at 216.405-2-71(b) as a result of changes under DFARS final rule 2013-D037, published on November 18, 2013.

6. Corrects e-CFR by removing subsections 225.370-1 through 225.370-6.

7. Corrects the hyperlink at 225.7401(b).

8. Removes table of contents heading at 227.7203-7.

9. Correct office designation at 252.225-7004 and 252.225-7006.

List of Subjects in 48 CFR Parts 201, 204, 212, 216, 225, 227, and 252

Government procurement.

Manuel Quinones,

Editor, Defense Acquisition Regulations System.

Therefore, 48 CFR Parts 201, 204, 212, 216, 225, 227, and 252 are amended as follows:

1. The authority citation for 48 CFR Parts 201, 204, 212, 216, 225, 227, and 252 continues to read as follows:

Authority: 41 U.S.C. 1303 and 48 CFR chapter 1.

PART 201--FEDERAL ACQUISITION REGULATIONS SYSTEM

201.603 [Amended]

2. Section heading at 201.603 is amended by removing ``termination of appointment'' and adding ``termination of appointment for contracting officers'' in its place.

203.906 [Amended]

3. Section 203.906(1) is amended by removing ``203.903;'' and adding ``203.903'' in its place.

PART 204--ADMINISTRATIVE MATTERS

204.7207 [Amended]

4. Section 204.7207 paragraph (a) is amended by removing the word ``clause'' and adding the word ``provision'' in its place.

PART 212--ACQUISITION OF COMMERCIAL ITEMS

212.301 [Amended]

5. Section 212.301 is amended by removing paragraph (f)(xlii) and redesignating (f)(xliii) through (lxviii) as (f)(xlii) through (lxvii).

PART 216--TYPES OF CONTRACTS

216.405-2-71 [Amended]

6. Section 216.405-2-71 paragraph (b) is amended by removing ``252.225-7039'' and adding ``FAR 52.225-26'' in its place.

PART 225--FOREIGN ACQUISITION

225.370-1 through 225.370-6 [Removed]

7. Remove sections 225.370-1 through 225.370-6.

225.7401 [Amended]

8. Section 225.7401 paragraph (b) is amended by removing ``http://www.per.hqusareur.army.mil/cpd/docper/GermanyDefault.aspx'' and adding ``http://www.eur.army.mil/g1/content/CPD/docper.html'' in its place.

PART 227--PATENTS, DATA, AND COPYRIGHTS

227.7203-7 [Removed]

9. Remove reserved section 227.7203-7.

PART 252--SOLICITATION PROVISIONS AND CONTRACT CLAUSES

252.225-7004 [Amended]

10. Section 252.225-7004 paragraph (c)(5) is amended by removing ``OUSD(AT&L)DPAP(CPIC),'' and adding ``OUSD(AT&L) DPAP/CPIC,'' in its place.

252.225-7006 [Amended]

11. Section 252.225-7006 paragraph (d) is amended by removing ``OUSD(AT&L)DPAP(CPIC)'' and adding ``OUSD(AT&L) DPAP/CPIC'' in its place.

[FR Doc. 2013-29146 Filed 12-5-13; 8:45 am]

BILLING CODE 5001-06-P

-----------------------------------------------------------------------

[Federal Register Volume 78, Number 235 (Friday, December 6, 2013)]

[Rules and Regulations]

From the Federal Register Online via the Government Printing Office [www.gpo.gov]

[FR Doc No: 2013-29153]

-----------------------------------------------------------------------

DEPARTMENT OF DEFENSE

Defense Acquisition Regulations System

48 CFR Part 225

RIN 0750-AH84

Defense Federal Acquisition Regulation Supplement: Preparation of Letter of Offer and Acceptance (DFARS Case 2012-D048)

AGENCY: Defense Acquisition Regulations System, Department of Defense (DoD).

ACTION: Final rule.

-----------------------------------------------------------------------

SUMMARY: DoD is issuing a final rule amending the Defense Federal

Acquisition Regulation Supplement (DFARS) to address the contracting officer role in assisting the DoD implementing agency in preparation of the letter of offer and acceptance for a foreign military sales program that will require an acquisition.

DATES: Effective December 6, 2013.

FOR FURTHER INFORMATION CONTACT: Ms. Amy Williams, telephone 571-372-6106.

SUPPLEMENTARY INFORMATION:

I. Background

DoD published a proposed rule in the Federal Register at 78 FR 28793 on May 16, 2013, to address the contracting officer role in assisting the DoD implementing agency in preparation of the letter of offer and acceptance for a foreign military sales program that will require an acquisition. No respondents submitted public comments in response to the proposed rule. There are no changes from the proposed rule in the final rule.

II. Executive Orders 12866 and 13563

Executive Orders (E.O.s) 12866 and 13563 direct agencies to assess all costs and benefits of available regulatory alternatives and, if regulation is necessary, to select regulatory approaches that maximize net benefits (including potential economic, environmental, public health and safety effects, distributive impacts, and equity). E.O. 13563 emphasizes the importance of quantifying both costs and benefits, of reducing costs, of harmonizing rules, and of promoting flexibility. This is not a significant regulatory action and, therefore, was not subject to review under section 6(b) of E.O. 12866, Regulatory Planning and Review, dated September 30, 1993. This rule is not a major rule under 5 U.S.C. 804.

III. Regulatory Flexibility Act

A final regulatory flexibility analysis has been prepared consistent with the Regulatory Flexibility Act, 5 U.S.C. 601, et seq., and is summarized as follows:

This action is necessary because the directions to the contracting officer at PGI 225.7302 may have impact on prospective contractors, and therefore require relocation to the DFARS. The objective of this rule is to provide direction to the contracting officer on actions required to work with the prospective contractor to assist the DoD implementing activity in preparing the letter of offer and acceptance for a foreign military sales program that requires an acquisition.

There were no comments in response to the initial regulatory flexibility analysis. The Chief Counsel for Advocacy of the Small Business Administration did not file any comments.

The rule will apply to approximately 380 small entities, based on the FPDS data for FY 2011 of the number of noncompetitive contract awards to small business entities that exceed $10,000 and use FMS funds.

There is no required reporting or recordkeeping. The rule requires the contracting officer to communicate with a prospective FMS contractor in order to assist the DoD implementing agency in preparation of the letter of offer and acceptance. The contracting officer may request information on price, delivery, and other relevant factors, and provide information to the prospective contractor with regard to the FMS customer.

DoD does not expect the rule will have a significant economic impact on a significant number of small entities. No significant alternatives were identified that would accomplish the objectives of the rule.

IV. Paperwork Reduction Act

The rule does not contain any information collection requirements that require the approval of the Office of Management and Budget under the Paperwork Reduction Act (44 U.S.C. chapter 35).

List of Subjects in 48 CFR Part 225

Government procurement.

Manuel Quinones,

Editor, Defense Acquisition Regulations System.

Therefore, 48 CFR Part 225 is amended as follows:

PART 225--FOREIGN ACQUISITION

1. The authority citation for 48 CFR Part 225 continues to read as follows:

Authority: 41 U.S.C. 1303 and 48 CFR chapter 1.

2. Section 225.7302 is revised to read as follows:

225.7302 Preparation of letter of offer and acceptance.

For FMS programs that will require an acquisition, the contracting officer shall assist the DoD implementing agency responsible for preparing the Letter of Offer and Acceptance (LOA) by--

(1) Working with prospective contractors to--

(i) Identify, in advance of the LOA, any unusual provisions or deviations (such as those requirements for Pseudo LOAs identified at PGI 225.7301);

(ii) Advise the contractor if the DoD implementing agency expands, modifies, or does not accept any key elements of the prospective contractor's proposal;

(iii) Identify any logistics support necessary to perform the contract (such as those requirements identified at PGI 225.7301); and

(iv) For noncompetitive acquisitions over $10,000, ask the prospective contractor for information on price, delivery, and other relevant factors. The request for information shall identify the fact that the information is for a potential foreign military sale and shall identify the foreign customer; and

(2) Working with the DoD implementing agency responsible for preparing the LOA, as specified in PGI 225.7302.

[FR Doc. 2013-29153 Filed 12-5-13; 8:45 am]

BILLING CODE 5001-06-P

-----------------------------------------------------------------------

[Federal Register Volume 78, Number 235 (Friday, December 6, 2013)]

[Rules and Regulations]

From the Federal Register Online via the Government Printing Office [www.gpo.gov]

[FR Doc No: 2013-29151]

-----------------------------------------------------------------------

DEPARTMENT OF DEFENSE

Defense Acquisition Regulations System

48 CFR Part 231

RIN 0750-AH76

Defense Federal Acquisition Regulation Supplement: Unallowable Fringe Benefit Costs (DFARS Case 2012-D038)

AGENCY: Defense Acquisition Regulations System, Department of Defense (DoD).

ACTION: Final rule.

-----------------------------------------------------------------------

SUMMARY: DoD is issuing a final rule amending the Defense Federal Acquisition Regulation Supplement (DFARS) to explicitly state that fringe benefit costs that are contrary to law, employer-employee agreement, or an established policy of the contractor are unallowable.

DATES: Effective December 6, 2013.

FOR FURTHER INFORMATION CONTACT: Ms. Susan Williams, telephone 571-372-6092.

SUPPLEMENTARY INFORMATION:

I. Background

DoD published a proposed rule in the Federal Register at 78 FR 13606 on February 28, 2013, to revise the DFARS at 231.205-6 to implement the Director of Defense Pricing policy memo ``Unallowable Costs for Ineligible Dependent Health Care Benefits'', dated February 17, 2012. This rule adds paragraph 231.205-6(m)(1) to explicitly state that fringe benefit costs that are contrary to law, employer-employee agreement, or an established policy of the contractor are unallowable.

II. Discussion and Analysis of Public Comments

DoD reviewed the public comments in the development of the final rule. A discussion of the comments and the changes made as a result of those comments is provided, as follows:

A. Summary of Significant Changes from the Proposed Rule

After consideration of a public comment, DoD determined that the reference to ``incurred or estimated'' within the DFARS text should be deleted.

B. Analysis of Public Comments

Two respondents submitted comments on the proposed rule.

1. Policy Memo Disagreement

Comment: One respondent disagreed with the conclusions of the Director of Defense Pricing policy memorandum. However, the respondent agreed that contractors should monitor healthcare dependent eligibility to ensure only proper healthcare charges are included as an element of fringe benefit costs.

Response: The memorandum emphasizes and clarifies existing policies but does not create new policies. These existing policies make fringe benefit costs unallowable when such costs are unreasonable or conflict with law, employer-employee agreement, or an established policy of the contractor. DoD shares the respondent's belief that contractors should have adequate internal controls to ensure improper healthcare charges are excluded from fringe benefit costs. The rule encourages contractors to adopt reasonable internal controls to eliminate costs that are already unallowable.

2. Broadening the Category of Fringe Benefits

Comment: One respondent took exception to the rule addressing the broad category of fringe benefits when the Director of Defense Pricing policy memorandum only addresses the cost of health care benefits for ineligible dependents.

Response: The policy at FAR 31.205-6(m) states, in part, that fringe benefit costs are allowable to the extent they are required by law, employer-employee agreement, or an established policy of the contractor. The DFARS policy memo addressed only the area that has experienced recent problems. Reasonable internal controls can significantly reduce the amount of ineligible dependent healthcare claims that are already unallowable if they fail to meet the conditions in FAR 31.205-6(m). The same logic applies to all fringe benefits.3. Immaterial and No-Impact

Comment: One respondent asserted that industry-wide ineligible dependent costs are immaterial, and thus have no impact on contract billing or pricing. The respondent suggested that DoD should review the DCAA findings in its policy memo 09-PSP-016(R), dated August 4, 2009, before proceeding with further rulemaking.

Response: Research indicates the rate of ineligible dependent claims can represent as much as 3 percent or more of total healthcare costs. The overall cost for ineligible dependent claims, which are often fraudulent, can be significant for large contractors that spend millions of dollars for dependent healthcare. Programs to reduce ineligible dependent healthcare claims have been shown to benefit both the contractor and its customers. Penalties may be assessed if unallowable dependent healthcare costs are contained in a final indirect cost rate proposal, or a final statement of costs incurred, or estimated to be incurred, under a fixed-price incentive contract.

4. Cost Accounting Standard

Comment: One respondent asserted that the treatment of ineligible fringe benefit costs as expressly unallowable does not comport with Cost Accounting Standard (CAS) 405 and its preambles. In the preamble of the original publication of CAS 405, the CAS Board explained its use of the term ``expressly'' in the definition of ``expressly unallowable cost'' as ``. . . that which is in direct and unmistakable terms.'' The respondent believed that ``fringe benefit costs . . . contrary to law, employer-employee agreement, or an established policy of the contractor'' are not direct and unmistakable costs.

Response: The rule makes fringe benefit costs expressly unallowable when such costs are contrary to law, employer-employee agreement, or an established policy of the contractor. The Director of Defense Pricing Policy determined these conditions are direct and unmistakable.

5. Overlapping Protection

Comment: One respondent asserted that the rule is unnecessary since the FAR cost principles already protect the Government. Contractors are currently required to exclude fringe benefit costs that do not meet the requirements for reasonableness per FAR 31.201-3.

Response: The results of the DCAA audits have made it clear that coverage is not sufficiently clear. The intent of the rule is to make fringe benefit costs expressly unallowable when such costs conflict with law, employer-employee agreement, or an established policy of the contractor. Unallowable fringe benefit costs, such as ineligible dependent healthcare claims, unnecessarily increase the cost of Government contracts. Because contractors are already required to exclude unallowable costs from final indirect cost rate proposals or a final statement or cost incurred, penalties will only accrue to contractors that fail to comply with rules that already exist.

6. Relationship to the Application of Penalties

Comment: One respondent was concerned that the proposed rule does not conform to the FAR as it relates to the application of penalties. The respondent indicated that FAR 42.709-1 is limited to applying penalties only to unallowable costs included in an indirect cost proposal. The respondent further stated that there is no language in FAR 42.709-1 about ``estimated'' costs and because of this the respondent asserted that the reference to estimated costs in the proposed rule must be deleted.

Response: While subsection FAR 42.709-1 does not expressly use the term ``estimated'', this subsection does state that the penalties discussed in the subsection ``apply to contracts covered by this section.'' FAR 42.709, entitled ``Scope,'' specifically covers the assessment of penalties for including unallowable indirect costs in indirect cost rate proposals, or the ``final statement of costs incurred or estimated to be incurred . . .'' (emphasis added). Nevertheless, DoD has deleted the phrase ``incurred or estimated'' from DFARS 231.205-6(m)(1).

7. Test of Reasonableness

Comment: One respondent suggested that the costs should be judged by the test of reasonableness and not treated as unallowable with the associated penalties. The proposed rule would make these costs unallowable, thus forcing companies to expend disproportionate sums to ensure no claims for costs include ineligible health care costs in order to avoid the penalties. According to the respondent, this would force companies to behave differently than companies in the commercial marketplace or the U.S. Government in managing these costs.

Response: Ineligible fringe benefit costs are already unallowable under existing regulations. Thus, the test for reasonableness does not apply because an unallowable cost cannot, by definition be reasonable. Per FAR 31.205-6(m), fringe benefit costs are only allowable to the extent they are reasonable and are required by law, employer-employee agreement, or an established policy of the contractor. The DFARS rule only makes expressly unallowable fringe benefit costs that contractors are already required to exclude from forward pricing rates, incurred cost proposals, and billings. Research indicates nearly 70 percent of commercial companies have implemented procedures to detect and eliminate ineligible dependent health care claims in order to reduce costs and remain competitive. Therefore, the effect of the rule is to make the DFARS consistent with current commercial practice.

8. Internal Controls

Comment: One respondent asserted that, if a company's internal controls are found to be unreasonable, the Government can cite the contractor for a business system deficiency and disallow cost. Dependent healthcare costs are allowable until eligibility ceases, so the Government should focus on the reasonableness of the company's internal controls (i.e., reasonableness test) versus the allowability test. A company should not be required to pay penalties if it has adequate internal controls to prevent charging the Government for ineligible dependent healthcare costs or recover and credit those costs back to the Government when they are charged.

Response: The rule makes ineligible dependent healthcare costs expressly unallowable, and subject to penalties, when such costs are contained in a final indirect cost rate proposal or a final statement of costs incurred, or estimated to be incurred, under a fixed-price incentive contract. Penalties may be waived in accordance with FAR 42.709-5(c).

9. Exceeding the Actual Costs of Ineligible Benefits

Comment: One respondent asserted that the costs of internal controls should not exceed the actual costs of the ineligible benefits. Treating the costs for ineligible dependent healthcare costs as unallowable is likely to force companies to spend more money than they would otherwise, in order to avoid the penalties associated with unallowable costs. The result will be increased allowable costs to the Government in exchange for little or no value.

Response: Research indicates the cost of ineligible dependent health care claims often far exceeds the cost of dependent verification programs. DoD was unable to find any studies or other evidence indicating that the cost to detect ineligible claims is higher than the cost savings.

10. Possible Disfavor for Those Who Are Fully or Partially Subject to CAS

Comment: One respondent asserted that the proposed rule has the effect of discriminating against companies that are fully or partially subject to CAS. The respondent asserted that, for those fully subject to CAS and those partially subject to CAS, the potential risk for liability for claiming unallowable costs is significant, while companies that are not subject to CAS have no such liability and do not face the possibility of False Claims Act prosecutions, Civil False Claims Act damages, qui tam lawsuits or debarment/suspension. A rule that allows companies subject to CAS to use a reasonable method for dealing with these costs will reduce the cost to the companies and reasonably protect the government from paying for the costs of ineligible dependent healthcare costs.

Response: The rule and, thus, the potential liability to incur penalties, apply equally to all contractors regardless of whether they are subject to CAS. Therefore, the rule does not discriminate against companies that are fully or partially subject to CAS. Additionally, the assertion that companies not subject to CAS do not face the possibility of False Claims Act prosecutions, Civil False Claims Act damages, qui tam lawsuits or debarment/suspension is inaccurate.

III. Executive Orders 12866 and 13563

Executive Orders (E.O.s) 12866 and 13563 direct agencies to assess all costs and benefits of available regulatory alternatives and, if regulation is necessary, to select regulatory approaches that maximize net benefits (including potential economic, environmental, public health and safety effects, distributive impacts, and equity). E.O. 13563 emphasizes the importance of quantifying both costs and benefits, of reducing costs, of harmonizing rules, and of promoting flexibility. This is not a significant regulatory action and, therefore, was not subject to review under section 6(b) of E.O. 12866, Regulatory Planning and Review, dated September 30, 1993. This rule is not a major rule under 5 U.S.C. 804.

IV. Regulatory Flexibility Act

A final regulatory flexibility analysis has been prepared consistent with the Regulatory Flexibility Act, 5 U.S.C. 601, et seq., and is summarized as follows: This final rule amends the Defense Federal Acquisition Regulation Supplement (DFARS) at 231.205-6 to explicitly state that fringe benefit costs incurred or estimated that are contrary to law, employer-employee agreement, or an established policy of the contractor are unallowable. After consideration of a public comment, DoD determined that the reference to ``incurred or estimated'' within the DFARS proposed rule text should be deleted.

The objective of this final rule is to explicitly state that fringe benefit costs incurred or estimated that are contrary to law, employer-employee agreement, or an established policy of the contractor are unallowable. Although fringe benefit costs that do not meet these criteria are not allowable, the Federal Acquisition Regulation (FAR) does not make them expressly unallowable. Specifying these fringe benefit costs are expressly unallowable in the DFARS makes the penalties at FAR 42.709-1 applicable if a contractor includes such unallowable fringe benefit costs in a final indirect cost rate proposal or in the final statement of costs incurred under a fixed-price incentive contract.

No comments were filed by the Chief Counsel for Advocacy of the Small Business Administration in response to the proposed rule.

DoD does not expect this final rule to have a significant economic impact on a substantial number of small entities within the meaning of the Regulatory Flexibility Act, 5 U.S.C. 601, et seq., because this rule merely provides clarification of existing policies by expressly stating that fringe benefit costs incurred or estimated that are contrary to law, employer-employee agreement, or an established policy of the contractor are unallowable.

The final rule imposes no reporting, recordkeeping, or other information collection requirements.

There are no known significant alternatives to the rule. The impact of this rule on small business is not expected to be significant.

V. Paperwork Reduction Act

The rule does not contain any information collection requirements that require the approval of the Office of Management and Budget under the Paperwork Reduction Act (44 U.S.C. chapter 35).

List of Subjects in 48 CFR Part 231

Government procurement.

Manuel Quinones,

Editor, Defense Acquisition Regulations System.

Therefore, 48 CFR part 231 is amended as follows:

PART 231--CONTRACT COST PRINCIPLES AND PROCEDURES

1. The authority citation for 48 CFR part 231 continues to read as follows:

Authority: 41 U.S.C. 1303 and CFR chapter 1.

2. Section 231.205-6 is amended by adding paragraph (m)(1) to read as follows:

231.205-6 Compensation for personal services.

* * * * *

(m)(1) Fringe benefit costs that are contrary to law, employer-employee agreement, or an established policy of the contractor are unallowable.

[FR Doc. 2013-29151 Filed 12-5-13; 8:45 am]

BILLING CODE 5001-06-P

-----------------------------------------------------------------------