252.215-7000 Pricing Adjustments.

As prescribed in 215.408(1), use the following clause:

PRICING ADJUSTMENTS (DEC 2012)

The term “pricing adjustment,” as used in paragraph (a) of the clauses entitled “Price Reduction for Defective Certified Cost or Pricing Data–Modifications,” “Subcontractor Certified Cost or Pricing Data,” and “Subcontractor Certified Cost or Pricing Data–Modifications,” means the aggregate increases and/or decreases in cost plus applicable profits.

(End of clause)

252.215-7001 Reserved.

252.215-7002 Cost Estimating System Requirements.

As prescribed in 215.408(2), use the following clause:

COST ESTIMATING SYSTEM REQUIREMENTS (DEC 2012)

(End of clause)

252.215-7003 Requirement for Submission of Data Other Than Certified Cost or Pricing Data—Canadian Commercial Corporation.

As prescribed at 215.408(3)(i), use the following provision:

REQUIREMENT FOR SUBMISSION OF DATA OTHER THAN CERTIFIED COST OR PRICING DATA—CANADIAN COMMERCIAL CORPORATION (JUL 2012)

(a) Submission of certified cost or pricing data is not required.

(b) Canadian Commercial Corporation shall obtain and provide the following:

(c) As specified in FAR 15.403-3(a)(4), an offeror who does not comply with a requirement to submit data that the U.S. Contracting Officer has deemed necessary to determine price reasonableness or cost realism is ineligible for award unless the head of the contracting activity determines that it is in the best interest of the Government to make the award to that offeror.

252.215-7004 Requirement for Submission of Data Other Than Certified Cost or Pricing Data—Modifications—Canadian Commercial Corporation.

As prescribed at 215.408(3)(ii), use the following clause:

REQUIREMENT FOR SUBMISSION OF DATA OTHER THAN CERTIFIED COST OR PRICING DATA—MODIFICATIONS—CANADIAN COMMERCIAL CORPORATION (OCT 2013)

This clause , in lieu of FAR 52.215-21, applies only if award is to the Canadian Commercial Corporation.

252.215-7005 Evaluation Factor for Employing or Subcontracting with Members of the Selected Reserve.

As prescribed in 215.370-3(a), use the following provision:

EVALUATION FACTOR FOR EMPLOYING OR SUBCONTRACTING WITH MEMBERS OF THE SELECTED RESERVE (OCT 2008)

(End of provision)

252.215-7006 Use of Employees or Individual Subcontractors Who are Members of the Selected Reserve.

As prescribed in 215.370-3(b), use the following clause:

USE OF EMPLOYEES OR INDIVIDUAL SUBCONTRACTORS WHO ARE MEMBERS OF THE SELECTED RESERVE (OCT 2008)

(End of clause)

252.215-7007 Notice of Intent to Resolicit.

As prescribed at 215.371-6, use the following provision:

NOTICE OF INTENT TO RESOLICIT (JUN 2012)

This solicitation provides offerors fewer than 30 days to submit proposals. In the event that only one offer is received in response to this solicitation, the Contracting Officer may cancel the solicitation and resolicit for an additional period of at least 30 days in accordance with 215.371-2.

252.215-7008 Only One Offer.

As prescribed at 215.408(4), use the following provision:

ONLY ONE OFFER (OCT 2013)

(End of provision)

252.215-7009 Proposal Adequacy Checklist.

As prescribed in 215.408(5), use the following provision:

PROPOSAL ADEQUACY CHECKLIST (JAN 2014)

The offeror shall complete the following checklist, providing location of requested information, or an explanation of why the requested information is not provided. In preparation of the offeror’s checklist, offerors may elect to have their prospective subcontractors use the same or similar checklist as appropriate.

PROPOSAL ADEQUACY CHECKLIST

 

REFERENCES

SUBMISSION

ITEM

PROPOSAL PAGE No.

If not provided EXPLAIN (may use continuation pages)

GENERAL INSTRUCTIONS

1.

FAR 15.408, Table 15-2, Section I Paragraph A

Is there a properly completed first page of the proposal per FAR 15.408 Table 15-2 I.A or as specified in the solicitation?

   

2.

FAR 15.408, Table 15-2, Section I Paragraph A(7)

Does the proposal identify the need for Government-furnished material/tooling/test equipment? Include the accountable contract number and contracting officer contact information if known.

   

3.

FAR 15.408, Table 15-2, Section I Paragraph A(8)

Does the proposal identify and explain notifications of noncompliance with Cost Accounting Standards Board or Cost Accounting Standards (CAS); any proposal inconsistencies with your disclosed practices or applicable CAS; and inconsistencies with your established estimating and accounting principles and procedures?

   

4.

FAR 15.408, Table 15-2, Section I,

Paragraph C(1)

FAR 2.101, “Cost or pricing data”

Does the proposal disclose any other known activity that could materially impact the costs?

This may include, but is not limited to, such factors as—

(1) Vendor quotations;

(2) Nonrecurring costs;

(3) Information on changes in production methods and in production or purchasing volume;

(4) Data supporting projections of business prospects and objectives and related operations costs;

(5) Unit-cost trends such as those associated with labor efficiency;

(6) Make-or-buy decisions;

(7) Estimated resources to attain business goals; and

(8) Information on management decisions that could have a significant bearing on costs.

   

5.

FAR 15.408, Table 15-2, Section I Paragraph B

Is an Index of all certified cost or pricing data and information accompanying or identified in the proposal provided and appropriately referenced?

   

6.

FAR 15.403-1(b)

Are there any exceptions to submission of certified cost or pricing data pursuant to FAR 15.403-1(b)? If so, is supporting documentation included in the proposal? (Note questions 18-20.)

   

7.

FAR 15.408, Table 15-2, Section I Paragraph C(2)(i)

Does the proposal disclose the judgmental factors applied and the mathematical or other methods used in the estimate, including those used in projecting from known data?

   

8.

FAR 15.408, Table 15-2, Section I Paragraph C(2)(ii)

Does the proposal disclose the nature and amount of any contingencies included in the proposed price?

   

9.

FAR 15.408 Table 15-2, Section II, Paragraph A or B

Does the proposal explain the basis of all cost estimating relationships (labor hours or material) proposed on other than a discrete basis?

   

10.

FAR 15.408, Table 15-2, Section I Paragraphs D and E

Is there a summary of total cost by element of cost and are the elements of cost cross-referenced to the supporting cost or pricing data? (Breakdowns for each cost element must be consistent with your cost accounting system, including breakdown by year.)

   

11.

FAR 15.408, Table 15-2, Section I Paragraphs D and E

If more than one Contract Line Item Number (CLIN) or sub Contract Line Item Number (sub-CLIN) is proposed as required by the RFP, are there summary total amounts covering all line items for each element of cost and is it cross-referenced to the supporting cost or pricing data?

   

12.

FAR 15.408, Table 15-2, Section I Paragraph F

Does the proposal identify any incurred costs for work performed before the submission of the proposal?

   

13.

FAR 15.408, Table 15-2, Section I Paragraph G

Is there a Government forward pricing rate agreement (FPRA)? If so, the offeror shall identify the official submittal of such rate and factor data. If not, does the proposal include all rates and factors by year that are utilized in the development of the proposal and the basis for those rates and factors?

   

COST ELEMENTS

MATERIALS AND SERVICES

14.

FAR 15.408, Table 15-2, Section II Paragraph A

Does the proposal include a consolidated summary of individual material and services, frequently referred to as a Consolidated Bill of Material (CBOM), to include the basis for pricing? The offeror’s consolidated summary shall include raw materials, parts, components, assemblies, subcontracts and services to be produced or performed by others, identifying as a minimum the item, source, quantity, and price.

   

SUBCONTRACTS (Purchased materials or services)

15.

DFARS 215.404-3

Has the offeror identified in the proposal those subcontractor proposals, for which the contracting officer has initiated or may need to request field pricing analysis?

   

16.

FAR 15.404-3(c)

FAR 52.244-2

Per the thresholds of FAR 15.404-3(c), Subcontract Pricing Considerations, does the proposal include a copy of the applicable subcontractor’s certified cost or pricing data?

   

17.

FAR 15.408, Table 15-2,

Note 1;

Section II Paragraph A

Is there a price/cost analysis establishing the reasonableness of each of the proposed subcontracts included with the proposal?

If the offeror’s price/cost analyses are not provided with the proposal, does the proposal include a matrix identifying dates for receipt of subcontractor proposal, completion of fact finding for purposes of price/cost analysis, and submission of the price/cost analysis?

   

EXCEPTIONS TO CERTIFIED COST OR PRICING DATA

18.

FAR 52.215-20

FAR 2.101,

“commercial item”

Has the offeror submitted an exception to the submission of certified cost or pricing data for commercial items proposed either at the prime or subcontractor level, in accordance with provision 52.215-20?

a. Has the offeror specifically identified the type of commercial item claim (FAR 2.101 commercial item definition, paragraphs (1) through (8)), and the basis on which the item meets the definition?

b. For modified commercial items (FAR 2.101 commercial item definition paragraph (3)); did the offeror classify the modification(s) as either—

i. A modification of a type customarily available in the commercial marketplace (paragraph (3)(i)); or

ii. A minor modification (paragraph (3)(ii)) of a type not customarily available in the commercial marketplace made to meet Federal Government requirements not exceeding the thresholds in FAR 15.403-1(c)(3)(iii)(B)?

c. For proposed commercial items “of a type”, or “evolved” or modified (FAR 2.101 commercial item definition paragraphs (1) through (3)), did the contractor provide a technical description of the differences between the proposed item and the comparison item(s)?

   

19.

 

[Reserved]

   

20.

FAR 15.408, Table 15-2, Section II Paragraph A(1)

Does the proposal support the degree of competition and the basis for establishing the source and reasonableness of price for each subcontract or purchase order priced on a competitive basis exceeding the threshold for certified cost or pricing data?

   

INTERORGANIZATIONAL TRANSFERS

21.

FAR 15.408, Table 15-2, Section II Paragraph A.(2)

For inter-organizational transfers proposed at cost, does the proposal include a complete cost proposal in compliance with Table 15-2?

   

22.

FAR 15.408, Table 15-2, Section II Paragraph A(1)

For inter-organizational transfers proposed at price in accordance with FAR 31.205-26(e), does the proposal provide an analysis by the prime that supports the exception from certified cost or pricing data in accordance with FAR 15.403-1?

   

DIRECT LABOR

23.

FAR 15.408, Table 15-2, Section II Paragraph B

Does the proposal include a time phased (i.e.; monthly, quarterly) breakdown of labor hours, rates and costs by category or skill level? If labor is the allocation base for indirect costs, the labor cost must be summarized in order that the applicable overhead rate can be applied.

   

24.

FAR 15.408, Table 15-2, Section II Paragraph B

For labor Basis of Estimates (BOEs), does the proposal include labor categories, labor hours, and task descriptions, (e.g.; Statement of Work reference, applicable CLIN, Work Breakdown Structure, rationale for estimate, applicable history, and time-phasing)?

   

25.

FAR subpart 22.10

If covered by the Service Contract Labor Standards statute (41 U.S.C. chapter 67), are the rates in the proposal in compliance with the minimum rates specified in the statute?

   

INDIRECT COSTS

26.

FAR 15.408, Table 15-2, Section II Paragraph C

Does the proposal indicate the basis of estimate for proposed indirect costs and how they are applied? (Support for the indirect rates could consist of cost breakdowns, trends, and budgetary data.)

   

OTHER COSTS

27.

FAR 15.408, Table 15-2, Section II Paragraph D

Does the proposal include other direct costs and the basis for pricing? If travel is included does the proposal include number of trips, number of people, number of days per trip, locations, and rates (e.g. airfare, per diem, hotel, car rental, etc)?

   

28.

FAR 15.408, Table 15-2, Section II Paragraph E

If royalties exceed $1,500 does the proposal provide the information/data identified by Table 15-2?

   

29.

FAR 15.408, Table 15-2, Section II Paragraph F

When facilities capital cost of money is proposed, does the proposal include submission of Form CASB-CMF or reference to an FPRA/FPRP and show the calculation of the proposed amount?

   

FORMATS FOR SUBMISSION OF LINE ITEM SUMMARIES

30.

FAR 15.408, Table 15-2, Section III

Are all cost element breakdowns provided using the applicable format prescribed in FAR 15.408, Table 15-2 III? (or alternative format if specified in the request for proposal)

   

31.

FAR 15.408, Table 15-2, Section III Paragraph B

If the proposal is for a modification or change order, have cost of work deleted (credits) and cost of work added (debits) been provided in the format described in FAR 15.408, Table 15-2.III.B?

   

32.

FAR 15.408, Table 15-2, Section III Paragraph C

For price revisions/redeterminations, does the proposal follow the format in FAR 15.408, Table 15-2.III.C?

   

OTHER

33.

FAR 16.4

If an incentive contract type, does the proposal include offeror proposed target cost, target profit or fee, share ratio, and, when applicable, minimum/maximum fee, ceiling price?

   

34.

FAR 16.203-4 and FAR

15.408 Table 15-2, Section II, Paragraphs A, B, C, and D

If Economic Price Adjustments are being proposed, does the proposal show the rationale and application for the economic price adjustment?

   

35.

FAR 52.232-28

If the offeror is proposing Performance-Based Payments did the offeror comply with FAR 52.232-28?

   

36.

FAR 15.408(n)

FAR 52.215-22

FAR 52.215-23

Excessive Pass-through Charges– Identification of Subcontract Effort: If the offeror intends to subcontract more than 70% of the total cost of work to be performed, does the proposal identify: (i) the amount of the offeror’s indirect costs and profit applicable to the work to be performed by the proposed subcontractor(s); and (ii) a description of the added value provided by the offeror as related to the work to be performed by the proposed subcontractor(s)?

   

(End of provision)

(Revised June 26, 2015)

252.216-7000 Economic Price Adjustment—Basic Steel, Aluminum, Brass, Bronze, or Copper Mill Products.

As prescribed in 216.203-4-70(a)(1), use the following clause:

ECONOMIC PRICE ADJUSTMENT—BASIC STEEL, ALUMINUM, BRASS, BRONZE, OR COPPER MILL PRODUCTS (MAR 2012)

(End of clause)

252.216-7001 Economic Price Adjustment–Nonstandard Steel Items.

As prescribed in 216.203-4-70(b), use the following clause:

ECONOMIC PRICE ADJUSTMENT--NONSTANDARD STEEL ITEMS (JUL 1997)

NOTES:

1 Offeror insert the unit price and unit measure of the standard steel mill item to be used in the manufacture of the contract item.

2 Offeror identify the standard steel mill item to be used in the manufacture of the contract item.

3 Offeror insert best estimate of the number of days required for processing the standard steel mill item in the shop identified under the “labor index” definition.

4 Offeror identify the shop and plant in which the standard steel mill item identified under the “base steel index” definition will be finally fabricated or processed into the contract item.

5 Offeror insert the same percentage figures for the corresponding blanks in paragraphs (b), (e)(3)(i), and (e)(3)(ii). In paragraph (e)(3)(iii), insert the percentage representing the difference between the sum of the percentages inserted in paragraph (b) and 100 percent.

6 In negotiated acquisitions of nonstandard steel items, when there is no “established price” or when it is not desirable to use this price, this paragraph may refer to another appropriate price basis, e.g., an established interplant price.

(End of clause)

252.216-7002 Alternate A, Time-and-Materials/Labor-Hour Proposal Requirements – Non-Commercial Item Acquisition with Adequate Price Competition.

As prescribed in 216.601(e), substitute the following paragraph (c) for paragraph (c) of the provision at FAR 52.216-29:

ALTERNATE A, TIME-AND-MATERIALS/LABOR-HOUR PROPOSAL REQUIREMENTS—NON-COMMERCIAL ITEM ACQUISITION WITH ADEQUATE PRICE COMPETITION (FEB 2007)

252.216-7003 Economic Price Adjustment—Wage Rates or Material Prices Controlled by a Foreign Government.

As prescribed in 216.203-4-70(c)(1), use the following clause:

ECONOMIC PRICE ADJUSTMENT—WAGE RATES OR MATERIAL PRICES CONTROLLED BY A FOREIGN GOVERNMENT (MAR 2012)

(End of clause)

252.216-7004 Award Fee Reduction or Denial for Jeopardizing the Health or Safety of Government Personnel.

As prescribed in 216.406, use the following clause:

AWARD FEE REDUCTION OR DENIAL FOR JEOPARDIZING THE HEALTH ORSAFETY OF GOVERNMENT PERSONNEL (SEP 2011)

(i) Means any incident in which the Contractor, through a criminal, civil, or administrative proceeding that results in a disposition listed in paragraph (a) (ii) of this definition –

results in –

(2) The payment of a reimbursement, restitution, or damages in excess of $100,000.

(b) If, in the performance of this contract, the Contractor’s or its subcontractor’s actions cause serious bodily injury or death of civilian or military Government personnel, the Government may reduce or deny the award fee for the relevant award fee period in which the covered incident occurred, including the recovery of all or part of any award fees paid for any previous period during which the covered incident occurred.

(End of clause)

252.216-7005 Award Fee.

As prescribed in 216.406(e)(2), insert the following clause:

AWARD FEE (FEB 2011)

The Contractor may earn award fee from a minimum of zero dollars to the maximum amount stated in the award-fee plan in this contract. In no event will award fee be paid to the Contractor for any evaluation period in which the Government rates the Contractor’s overall cost, schedule, and technical performance below satisfactory. The Contracting Officer may unilaterally revise the award-fee plan prior to the beginning of any rating period in order to redirect contractor emphasis.

(End of clause)

252.216-7006 Ordering.

As prescribed in 216.506(a), use the following clause:

ORDERING (MAY 2011)

(a) Any supplies and services to be furnished under this contract shall be ordered by issuance of delivery orders or task orders by the individuals or activities designated in the contract schedule. Such orders may be issued from __________ through ____________ [insert dates].

(b) All delivery orders or task orders are subject to the terms and conditions of this contract. In the event of conflict between a delivery order or task order and this contract, the contract shall control.

(c)(1) If issued electronically, the order is considered “issued” when a copy has been posted to the Electronic Document Access system, and notice has been sent to the Contractor.

(End of Clause)

252.216-7007 Economic Price Adjustment—Basic Steel, Aluminum, Brass, Bronze, or Copper Mill Products—Representation.

As prescribed in 216.203-4-70(a)(2), use the following provision:

ECONOMIC PRICE ADJUSTMENT—BASIC STEEL, ALUMINUM, BRASS, BRONZE, OR COPPER MILL PRODUCTS—REPRESENTATION (MAR 2012)

(End of provision)

252.216-7008 Economic Price Adjustment—Wage Rates or Material Prices Controlled by a Foreign Government—Representation.

As prescribed in 216.203-4-70(c)(2), use the following provision:

ECONOMIC PRICE ADJUSTMENT—WAGE RATES OR MATERIAL PRICES CONTROLLED BY A FOREIGN GOVERNMENT—REPRESENTATION (MAR 2012)

(End of provision)

252.216-7009 Allowability of Legal Costs Incurred in Connection With a Whistleblower Proceeding.

As prescribed in 216.307(a), use the following clause:

ALLOWABILITY OF LEGAL COSTS INCURRED IN CONNECTION WITH A WHISTLEBLOWER PROCEEDING (SEP 2013)

Pursuant to section 827 of the National Defense Authorization Act for Fiscal Year 2013 (Pub. L. 112-239), notwithstanding FAR clause 52.216-7, Allowable Cost and Payment—

(End of clause)

252.216-7010 Requirements.

REQUIREMENTS—BASIC (APR 2014)

(End of clause)

REQUIREMENTS—ALTERNATE I (APR 2014)

(End of clause)

(Revised June 26, 2015)

252.217-7000 Exercise of Option to Fulfill Foreign Military Sales Commitments.

EXERCISE OF OPTION TO FULFILL FOREIGN MILITARY SALES
COMMITMENTS—BASIC (NOV 2014)

(Insert name of country)

 

(Insert applicable CLIN)

(End of clause)

which uses a different paragraph (b) than paragraph (b) of the basic clause:

EXERCISE OF OPTION TO FULFILL FOREIGN MILITARY SALES COMMITMENTS—ALTERNATE I (NOV 2014)

(End of clause)

252.217-7001 Surge Option.

As prescribed in 217.208-70(b), use the following clause:

SURGE OPTION (AUG 1992)

(End of clause)

252.217-7002 Offering Property for Exchange.

As prescribed in 217.7005, use the following provision:

OFFERING PROPERTY FOR EXCHANGE (JUN 2012)

(End of provision)

252.217-7003 Changes.

As prescribed in 217.7104(a), use the following clause:

CHANGES (DEC 1991)

(End of clause)

252.217-7004 Job Orders and Compensation.

As prescribed in 217.7104(a), use the following clause:

JOB ORDERS AND COMPENSATION (MAY 2006)

(End of clause)

252.217-7005 Inspection and Manner of Doing Work.

As prescribed in 217.7104(a), use the following clause:

INSPECTION AND MANNER OF DOING WORK (JUL 2009)

(End of clause)

252.217-7006 Title.

As prescribed in 217.7104(a), use the following clause:

TITLE (DEC 1991)

(End of clause)

252.217-7007 Payments.

As prescribed in 217.7104(a), use the following clause:

PAYMENTS (DEC 1991)

(End of clause)

252.217-7008 Bonds.

As prescribed in 217.7104(a), use the following clause:

BONDS (DEC 1991)

(End of clause)

252.217-7009 Default.

As prescribed in 217.7104(a), use the following clause:

DEFAULT (DEC 1991)

(End of clause)

252.217-7010 Performance.

As prescribed in 217.7104(a), use the following clause:

PERFORMANCE (JUL 2009)

(End of clause)

252.217-7011 Access to Vessel.

As prescribed at 217.7104(a), use the following clause:

ACCESS TO VESSEL (DEC 1991)

(End of clause)

252.217-7012 Liability and Insurance.

As prescribed in 217.7104(a), use the following clause:

LIABILITY AND INSURANCE (AUG 2003)

(End of clause)

252.217-7013 Guarantees.

As prescribed in 217.7104(a), use the following clause:

GUARANTEES (DEC 1991)

(End of clause)

252.217-7014 Discharge of Liens.

As prescribed in 217.7104(a), use the following clause:

DISCHARGE OF LIENS (DEC 1991)

(End of clause)

252.217-7015 Safety and Health.

As prescribed in 217.7104(a), use the following clause:

SAFETY AND HEALTH (DEC 1991)

Nothing contained in the Master Agreement or any job order shall relieve the Contractor of any obligations it may have to comply with—

(End of clause)

252.217-7016 Plant Protection.

As prescribed in 217.7104(a), use the following clause:

PLANT PROTECTION (DEC 1991)

(End of clause)

252.217-7017 Reserved.

252.217-7018 Reserved.

252.217-7019 Reserved.

252.217-7020 Reserved.

252.217-7021 Reserved.

252.217-7022 Reserved.

252.217-7023 Reserved.

252.217-7024 Reserved.

252.217-7025 Reserved.

252.217-7026 Identification of Sources of Supply.

As prescribed in 217.7303, use the following provision:

IDENTIFICATION OF SOURCES OF SUPPLY (NOV 1995)

TABLE

 

National

Commercial

Source of Supply

Actual

Line

Stock

Item

Company

Address

Part No.

Mfg?

Items

Number

(Y or N)

       

(1)

(2)

(3)

(4)

(4)

(5)

(6)

______

________

__________

_________

_______

________

_______

(1) List each deliverable item of supply and item of technical data.

(2) If there is no national stock number, list “none.”

(3) Use “Y” if the item is a commercial item; otherwise use “N.” If “Y” is listed, the Offeror need not complete the remaining columns in the table.

(4) For items of supply, list all sources. For technical data, list the source.

(5) For items of supply, list each source's part number for the item.

(6) Use “Y” if the source of supply is the actual manufacturer; “N” if it is not; and “U” if unknown.

(End of provision)

252.217-7027 Contract Definitization.

As prescribed in 217.7406(b), use the following clause:

CONTRACT DEFINITIZATION (DEC 2012)

or cost-and-fee) proposal and certified cost or pricing data supporting its proposal.

plans and certified cost or pricing data):

 
 
 

(End of clause)

252.217-7028 Over and Above Work.

As prescribed in 217.7702, use a clause substantially as follows:

OVER AND ABOVE WORK (DEC 1991)

(End of clause)

(Revised March 25, 2016)

252.219-7000 Advancing Small Business Growth.

As prescribed in 219.309(1), use the following provision:

ADVANCING SMALL BUSINESS GROWTH (MAY 2015)

(End of provision)

252.219-7001 Reserved.

252.219-7002 Reserved.

252.219-7003 Small Business Subcontracting Plan (DoD Contracts).

SMALL BUSINESS SUBCONTRACTING PLAN (DOD CONTRACTS)—BASIC (MAR 2016)

This clause supplements the Federal Acquisition Regulation 52.219-9, Small Business Subcontracting Plan, clause of this contract.

(End of clause)

SMALL BUSINESS SUBCONTRACTING PLAN (DOD CONTRACTS)—ALTERNATE I (MAR 2016)

This clause supplements the Federal Acquisition Regulation 52.219-9, Small Business Subcontracting Plan, clause of this contract.

(End of clause)

252.219-7004 Small Business Subcontracting Plan (Test Program).

As prescribed in 219.708(b)(1)(B), use the following clause:

SMALL BUSINESS SUBCONTRACTING PLAN (TEST PROGRAM) (OCT 2014)

“Electronic Subcontracting Reporting System (eSRS)” means the Governmentwide, electronic, web-based system for small business subcontracting program reporting. The eSRS is located at http://www.esrs.gov.

(End of clause)

252.219-7005 Reserved.

252.219-7006 Reserved.

252.219-7007 Reserved.

252.219-7008 Reserved.

252.219-7009 Section 8(a) Direct Award.

As prescribed in 219.811-3(1), use the following clause:

SECTION 8(a) DIRECT AWARD (SEP 2007)

________________________________________

________________________________________

________________________________________

________________________________________

[To be completed by the Contracting Officer
at the time of award]

(End of clause)

252.219-7010 Notification of Competition Limited to Eligible 8(a) Concerns—Partnership Agreement

As prescribed in 219.811-3(2), use the following clause:

NOTIFICATION OF COMPETITION LIMITED TO ELIGIBLE 8(A) CONCERNS—PARTNERSHIP AGREEMENT (MAR 2016)

(End of clause)

252.219-7011 Notification to Delay Performance.

As prescribed in 219.811-3(3), use the following clause:

NOTIFICATION TO DELAY PERFORMANCE (JUN 1998)

The Contractor shall not begin performance under this purchase order until 2 working days have passed from the date of its receipt. Unless the Contractor receives notification from the Small Business Administration that it is ineligible for this 8(a) award, or otherwise receives instructions from the Contracting Officer, performance under this purchase order may begin on the third working day following receipt of the purchase order. If a determination of ineligibility is issued within the 2-day period, the purchase order shall be considered canceled.