Previous PageTable Of ContentsSOFARSNext Page

SOFARS PART 5627PATENTS, DATA, AND COPYRIGHTS



SOFARS PART 5627 - PATENTS, DATA AND COPYRIGHTS
SUBPART 5627.3 - PATENT RIGHTS UNDER GOVERNMENT CONTRACTS
5627.305 Administration of Patent Rights.
5627.305-3
Follow-up by Government.
SUBPART 5627.70 - INFRINGEMENT CLAIMS, LICENSES, AND ASSIGNMENTS
5627.7004
Requirements for Filing an Administrative Claim for Patent Infringements.

SOFARS PART 5627
PATENTS, DATA, AND COPYRIGHTS

SUBPART 5627.3 - PATENT RIGHTS UNDER GOVERNMENT CONTRACTS

5627.305 Administration of Patent Rights.


5627.305-3 Follow-up by Government.
(Revised April 2011)
(a) Upon receipt of a DD form 882, Report of Inventions and Subcontracts, as prescribed in DFARS 227.304-1, or a letter prepared in accordance with relevant patent rights clause(s), contracting officers shall immediately forward the submission to the RAO to confirm that the contractor has reported all subject inventions. Forward the DD882 or other submission, along with the RAO input, to legal counsel for review and appropriate action.
(b) No legal review of the DD882 is required for phase I SBIR contracts if:

SUBPART 5627.70 - INFRINGEMENT CLAIMS, LICENSES, AND ASSIGNMENTS

5627.7004 Requirements for Filing an Administrative Claim for Patent Infringements.
(Revised July 2010) (Revised September 2013-reorganization)
(c) All contracting offices shall acknowledge receipt of patent right allegations and then forward a copy of the documents to SOF AT&L-KM or SOF AT&L-KX as appropriate, and legal counsel.

HQ, United States Special Operations Command
Special Operations Forces Acquisition, Technology, and Logistics (SOF AT&L-K)
SOFARS 5627
February 2007

Previous PageTop Of PageTable Of ContentsSOFARSNext Page